• Summary
  • Projects
  • Utilities
  • Certificate Public Good
  • FAQ

VermontSPEED
  • Summary
  • Projects
  • Utilities
  • Certificate Public Good
  • FAQ

SPEED PROGRAM
  • Summary
  • Projects
  • Utilities
  • Certificate Public Good
  • FAQ
STANDARD OFFER PROGRAM
  • Summary
  • Contract
  • Rates
  • Application
  • Application Instructions
  • SPEED Certification
  • 150 kW or Less
  • Applications Being Processed
  • Applications Not Yet Processed
  • Technology Lotteries
  • Standard Offer Versus Net Metering
  • Board Orders
  • FAQ
SPEED PRODUCTION
  • SPEED Monthly Production
  • SPEED Prorata Share
  • SPEED REC Distribution

 

 

Standard Offer FAQs > Site Control > I’m in negotiations with a landowner for site control. I not able to complete these negotiations until after I find out if I am in the queue. Will this be a problem?

Search the FAQ for entries containing:

Yes.  You must demonstrate that you had site control at the time that you completed the application to enter the queue or you will be removed from the queue.

 